The most misunderstood role in construction.
The superintendent – independent certifier or principal’s agent?
In a perfect world, construction projects would run smoothly.
Principals would have perfect drawings and perfect specifications which set out exactly what to build and even, notes on how to build it. With this perfect information, builders would know exactly what difficulties to expect when building, plan accordingly, and deliver each project perfectly on time and for the originally agreed price.
Unfortunately, we don’t live in a perfect world.
Principal’s drawings/specifications are often grossly incomplete, don’t make sense, or they simply change their mind about what they want.
Builders also don’t really have any way to perfectly plan out the works.
To deal with these uncertainties, construction contracts are flexible and allow:
- Payments to be made progressively, depending on how much of the work has been completed up to that point;
- The price to increase or decrease, depending on whether the principal wants more work or less work carried out than originally agreed; and
- The amount of time to complete the work to increase or decrease, depending on if there are any issues which caused the work to be delayed.
Of course, each contract has tens (or sometimes, hundreds) of other clauses, terms, and conditions – but at their core, construction contracts deal with changes to the price and timing for construction work.
Given this ability to change, who should decide:
Common Issue no. 2 – To what extent is the superintendent an agent of the principal?
When reviewing a contract, it is crucial to examine the roles that the superintendent is tasked with fulfilling. If the superintendent has the authority to give directions on behalf of the principal, then it is acting as the principal’s representative when not performing functions as a superintendent.
This is important in cases where the principal issues a direction to carry out variation works, but the contract specifies that only the superintendent has the authority to do so. In such a scenario, the contractor may not have to comply with the principal’s direction because the principal did not have the contractual power to issue it.
Contractors should be cautious: if a contractor receives a direction from the principal, and the principal isn’t entitled to issue that direction, the contractor should request that the superintendent confirm it.
Common Issue no. 3 – What if there is no superintendent?
Most contracts expressly require the principal to ensure that a superintendent is appointed. For example, AS 4000 series contracts require:
“The Principal shall ensure that at all times there is a Superintendent, and that the Superintendent fulfils all aspects of the role and functions reasonably and in good faith.”
If the superintendent is removed from the contract (due to resignation, a falling out, or other reasons), and no substitute is appointed, who then fulfills the superintendent’s role?
The answer: no one. This issue was highlighted in Niclin v SHA, where the payment certificate was issued by the principal’s in-house legal counsel instead of the superintendent. The court found the certificate invalid because it wasn’t issued by the superintendent, leading to the claimant’s only option being to terminate the contract and sue for damages.
To avoid this issue, contracts can include clauses such as:
-
Deeming the progress claim as certified if not responded to within a certain timeframe:
“If the Superintendent does not issue the progress certificate within 14 days of receiving a progress claim in accordance with subclause [insert], that progress claim shall be deemed to be the relevant progress certificate.” -
Deeming the principal as the superintendent if no superintendent is appointed:
“If at any time there is no Superintendent appointed under the Contract, the Principal shall be deemed to be the Superintendent until a new Superintendent has been appointed and shall be authorized to fulfill all aspects of the Superintendent’s role under the Contract.”
Common Issue no. 4 – Impartiality of the superintendent
In traditional contracts, the architect or engineer who documented the project usually assumes the role of the superintendent. By the time the contract is executed, the architect/engineer likely has a close, ongoing relationship with the principal, which may lead to biases favoring the principal.
In a design and construct contract, the same architect/engineer who prepared the preliminary design may later be engaged by the contractor to finalize the design, meaning the superintendent may act on behalf of the contractor.
In both scenarios, maintaining impartiality can be challenging because the superintendent may also be an agent for either the principal or the contractor. Superintendents must ensure they remain impartial when acting as certifiers.
In Vestas – Australian Wind Technology Pty Ltd v Lal Lal Wind Farm Nom Co Pty Ltd [2020] VSC 554, a contractor sought an injunction for all correspondence between the superintendent and principal to be made available. While the application was dismissed, Justice Delaney emphasized that private communications could undermine the independence of the superintendent, potentially rendering the decision void and breaching the contract.
Most contracts require the principal to ensure that the superintendent carries out its functions fairly and reasonably. If the principal unduly influences the superintendent’s decision, the resulting certificate may be invalid, and the contractor’s progress claim could be deemed valid and entitled to the full claimed amount.
Concluding Thoughts
The role of the superintendent is indeed fraught with challenges. On one hand, they are typically paid by the principal and expected to align with the principal’s interests, like most consultants. On the other hand, they have a responsibility to act impartially, balancing the needs of both the principal and the contractor. Ironically, if the superintendent blindly follows the principal’s instructions, they may end up causing more harm than good, even to the principal, by compromising their impartiality.
Over the past decade, it became common for employees, consultants, or directors of the principal to fulfill the superintendent’s role. This practice often led to disputes and litigation due to the absence of an objective certifier on projects.
Recently, there has been a trend toward appointing third-party experts as superintendents—experts with a deep understanding of contract administration, design management, and procurement. This shift aims to restore the impartiality that was central to the original role of the superintendent.
The hope is that the return of the “impartial superintendent” will reduce the frequency of disputes in construction projects, ultimately improving the industry’s efficiency and fairness.
— Alex Tuhtan – Shand Taylor Lawyers
— Dan Everett – EVERETT Property Development Management
Property Development Manager & Superintendent